Date Filed | Doc # | Docket Text |
|
2012-01-31 | 1 | COMPLAINT against DEFENSE COMMISSARY AGENCY ( Filing fee $ 350, receipt number 4616045650) filed by E&E ENTERPRISES GLOBAL, INC. (Attachments: # 1 Exhibit 1, # 2 Exhibit 2, # 3 Exhibit 3, # 4 Exhibit 4, # 5 Exhibit 5, # 6 Exhibit 6, # 7 Exhibit 7, # 8 Civil Cover Sheet)(rdj) (Entered: 02/01/2012) |
2012-01-31 | | SUMMONS (3) Issued as to DEFENSE COMMISSARY AGENCY, U.S. Attorney and U.S. Attorney General (rdj) (Entered: 02/01/2012) |
2012-01-31 | 2 | LCvR 7.1 CERTIFICATE OF DISCLOSURE of Corporate Affiliations and Financial Interests by E&E ENTERPRISES GLOBAL, INC. identifying Corporate Parent NONE for E&E ENTERPRISES GLOBAL, INC. (rdj) (Entered: 02/01/2012) |
2012-02-02 | 3 | ORDER Establishing Procedures for Filing for Cases Assigned to Judge Colleen Kollar-Kotelly, signed on February 2, 2012. (SM) (Entered: 02/02/2012) |
2012-02-22 | 4 | NOTICE of Appearance by Mitchell P. Zeff on behalf of DEFENSE COMMISSARY AGENCY (Zeff, Mitchell) (Entered: 02/22/2012) |
2012-02-23 | 5 | Consent MOTION for Extension of Time to Answer or Otherwise Respond to Plaintiff's Complaint by DEFENSE COMMISSARY AGENCY (Attachments: # 1 Text of Proposed Order)(Zeff, Mitchell) (Entered: 02/23/2012) |
2012-02-23 | 6 | RETURN OF SERVICE/AFFIDAVIT of Summons and Complaint Executed as to the United States Attorney. Date of Service Upon United States Attorney on 2/1/2012. Answer due for ALL FEDERAL DEFENDANTS by 3/2/2012. (Loveland, Christopher) (Entered: 02/23/2012) |
2012-02-23 | 7 | RETURN OF SERVICE/AFFIDAVIT of Summons and Complaint Executed on United States Attorney General. Date of Service Upon United States Attorney General 02/01/2012. (Loveland, Christopher) (Entered: 02/23/2012) |
2012-02-23 | 8 | RETURN OF SERVICE/AFFIDAVIT of Summons and Complaint Executed. DEFENSE COMMISSARY AGENCY served on 2/7/2012 (Loveland, Christopher) (Entered: 02/23/2012) |
2012-02-23 | | MINUTE ORDER granting 5 Defendant's Consent Motion for Extension of Time to Answer or Otherwise Respond to Plaintiff's Complaint. Accordingly, Defendant shall have until and including April 2, 2012, to Answer or Otherwise Respond to Plaintiff's Complaint. Set/Reset Deadline: Answer due by 4/2/2012. Signed by Judge Colleen Kollar-Kotelly on February 23, 2012. (SM) (Entered: 02/23/2012) |
2012-03-29 | 9 | Consent MOTION for Extension of Time to Answer or Otherwise Respond to Plaintiff's Complaint by DEFENSE COMMISSARY AGENCY (Attachments: # 1 Text of Proposed Order)(Zeff, Mitchell) (Entered: 03/29/2012) |
2012-03-29 | | MINUTE ORDER granting 9 Defendant's Consent Motion for Extension of Time to Answer or Otherwise Respond to Plaintiff's Complaint. Accordingly, Defendant shall have until and including May 18, 2012, to answer or otherwise respond to the compliant. Set/Reset Deadline: Answer due by 5/18/2012. Signed by Judge Colleen Kollar-Kotelly on March 29, 2012. (SM) (Entered: 03/29/2012) |
2012-05-16 | 10 | MOTION for Extension of Time to Respond to Complaint and Motion for Order to Set Briefing Schedule by DEFENSE COMMISSARY AGENCY (Attachments: # 1 Text of Proposed Order)(Zeff, Mitchell) (Entered: 05/16/2012) |
2012-05-16 | 11 | MOTION for Order to Set Briefing Schedule and For Extension of Time to Respond to Complaint by DEFENSE COMMISSARY AGENCY (Attachments: # 1 Text of Proposed Order)(Zeff, Mitchell) (Entered: 05/16/2012) |
2012-05-17 | 12 | ENTERED IN ERROR.....Memorandum in opposition to re 11 MOTION for Order to Set Briefing Schedule and For Extension of Time to Respond to Complaint , 10 MOTION for Extension of Time to Respond to Complaint and Motion for Order to Set Briefing Schedule filed by E&E ENTERPRISES GLOBAL, INC.. (Attachments: # 1 Exhibit 1, # 2 Exhibit 2, # 3 Exhibit 3, # 4 Exhibit 4, # 5 Exhibit 5, # 6 Text of Proposed Order)(Loveland, Christopher) Modified on 5/17/2012 (rdj). (Entered: 05/17/2012) |
2012-05-17 | | NOTICE OF CORRECTED DOCKET ENTRY: re 12 Memorandum in Opposition, was entered in error at the request of counsel and counsel will refile said pleading. (rdj) (Entered: 05/17/2012) |
2012-05-17 | 13 | Memorandum in opposition to re 11 MOTION for Order to Set Briefing Schedule and For Extension of Time to Respond to Complaint , 10 MOTION for Extension of Time to Respond to Complaint and Motion for Order to Set Briefing Schedule filed by E&E ENTERPRISES GLOBAL, INC.. (Attachments: # 1 Exhibit 1, # 2 Exhibit 2, # 3 Exhibit 3, # 4 Exhibit 4, # 5 Exhibit 5, # 6 Text of Proposed Order)(Loveland, Christopher) (Entered: 05/17/2012) |
2012-05-18 | | MINUTE ORDER (paperless). Upon consideration of Defendant's 10 11 Motion for Extension of Time to Respond to Complaint and Motion for Order to Set Briefing Schedule, and Plaintiff's 13 Opposition to Defendant's Motion for Extension of Time to Respond to Complaint and for Order to Set Briefing Schedule, the parties shall adhere to the following schedule: by no later than JUNE 1, 2012, Defendant shall (a) serve a final and complete Vaughn index upon Plaintiff, and (b) file an Answer to the 1 Complaint; thereafter, the parties shall promptly meet and confer in an attempt to narrow the areas of dispute, if any, and by no later than JUNE 11, 2012, shall file a Joint Status Report (a) briefly describing any remaining disputes and (b) proposing a schedule for further proceedings. Signed by Judge Colleen Kollar-Kotelly on May 18, 2012. (lcckk3) (Entered: 05/18/2012) |
2012-05-24 | 14 | Consent MOTION for Extension of Time to Serve a Final and Complete Vaughn Index Upon Plaintiff by DEFENSE COMMISSARY AGENCY (Attachments: # 1 Text of Proposed Order)(Zeff, Mitchell) (Entered: 05/24/2012) |
2012-05-24 | 15 | ANSWER to 1 Complaint, by DEFENSE COMMISSARY AGENCY.(Zeff, Mitchell) (Entered: 05/24/2012) |
2012-05-25 | | MINUTE ORDER granting 14 Defendant's Consent Motion for Extension of Time to Serve a Final and Complete Vaughn Index Upon Plaintiff. Accordingly, Defendant shall have until and including June 6, 2012, to serve a final and complete Vaughn Index upon Plaintiff. Signed by Judge Colleen Kollar-Kotelly on May 25, 2012.(SM) (Entered: 05/25/2012) |
2012-06-11 | 16 | STATUS REPORT (Joint) by DEFENSE COMMISSARY AGENCY, E&E ENTERPRISES GLOBAL, INC.. (Loveland, Christopher) (Entered: 06/11/2012) |
2012-06-12 | | MINUTE ORDER (paperless). The Court is in receipt of the parties' 16 Joint Status Report dated June 11, 2012, wherein they jointly propose a schedule for briefing motions for summary judgment. By a Scheduling and Procedures Order entered this same date, the Court shall adopt a modified version of the parties' proposed schedule. The Court finds that a staggered briefing schedule, as opposed to both parties filing their motions simultaneously, is preferable, as it will allow the parties to focus their attention on the central issues in dispute and ensure that their arguments are in direct conversation. Signed by Judge Colleen Kollar-Kotelly on June 12, 2012. (lcckk3) (Entered: 06/12/2012) |
2012-06-12 | 17 | SCHEDULING AND PROCEDURES ORDER. In order to administer this civil action in a manner fair to the litigants and consistent with the parties' interest in completing this litigation in the shortest possible time and at the least possible cost, the parties are directed to comply with each of the directives set forth in this Order. In addition, the parties shall adhere to the following schedule: Defendant shall file its motion for summary judgment by no later than June 29, 2012; Plaintiff shall file its opposition to Defendant's motion for summary judgment and its cross-motion for summary judgment by no later than July 16, 2012; Defendant shall file its reply in support of its motion for summary judgment and its opposition to Defendant's cross-motion for summary judgment by no later than August 2, 2012; and Plaintiff shall file its reply in support of its cross-motion for summary judgment by no later than August 13, 2012. Signed by Judge Colleen Kollar-Kotelly on June 12, 2012. (lcckk3) (Entered: 06/12/2012) |
2012-06-29 | 18 | MOTION for Summary Judgment by DEFENSE COMMISSARY AGENCY (Attachments: # 1 Exhibit, # 2 Text of Proposed Order)(Zeff, Mitchell) (Entered: 06/29/2012) |
2012-07-16 | 19 | Memorandum in opposition to re 18 MOTION for Summary Judgment and Cross-Motion For Summary Judgment filed by E&E ENTERPRISES GLOBAL, INC.. (Loveland, Christopher) (Entered: 07/16/2012) |
2012-07-16 | 20 | RESPONSE re 18 MOTION for Summary Judgment to Defendant's Statement of Material Facts In Support of Motion for Summary Judgment filed by E&E ENTERPRISES GLOBAL, INC.. (Loveland, Christopher) (Entered: 07/16/2012) |
2012-07-16 | 21 | Cross MOTION for Summary Judgment by E&E ENTERPRISES GLOBAL, INC. (See Docket Entry 19 to view document. Counsel is reminded to file the motion as a separate docket entry in future). (znmw, ) (Entered: 07/17/2012) |
2012-08-02 | 22 | NOTICE of Settlement Agreement in Principle (Joint) by DEFENSE COMMISSARY AGENCY (Zeff, Mitchell) (Entered: 08/02/2012) |
2012-08-03 | 23 | ORDER - Pursuant to 22 Joint Notice of Settlement Agreement in Principle, signed by the parties on August 2, 2012, this case is hereby dismissed. The dismissal shall be without prejudice for a period of 30 days, until September 4, 2012, to allow time for the parties to finalize the Settlement Agreement and obtain all necessary approvals. Signed by Judge Colleen Kollar-Kotelly on August 3, 2012. (SM) (Entered: 08/03/2012) |
Hide Docket Events |